Scheduled maintenance

Network fabric upgrade — EU Central

Leaf switches in EU Central (Frankfurt) will be upgraded pair by pair. Each rack loses one of its two uplinks for a few minutes; traffic continues on the other.

Reference 0ae134734e9d · EU Central (Frankfurt) · Updated just now

Status
CompletedCompleted — last update 19 Dec 2024, 02:35 UTC
Started
19 Dec, 01:00Thursday 19 December 2024 UTC
Duration
1 h 35 minEnded 19 Dec 2024, 02:35 UTC
Components
1Network and public IPs — EU Central (Frankfurt)
Timeline

The window, as announced and as it ran.

Completed3 updates · UTC
  1. CompletedThe maintenance is complete and every component is back to normal operation.19 Dec, 02:35
  2. In progressThe maintenance window has started.19 Dec, 01:00
  3. ScheduledLeaf switches in EU Central (Frankfurt) will be upgraded pair by pair. Each rack loses one of its two uplinks for a few minutes; traffic continues on the other. Expected impact: Up to 30 seconds of packet loss per rack, twice, when links fail over.12 Dec, 01:00

Affected components

Details

Type
Scheduled maintenance
Started
19 Dec 2024, 01:00 UTC
Ended
19 Dec 2024, 02:35 UTC
Region
EU Central (Frankfurt)
Expected impact
Up to 30 seconds of packet loss per rack, twice, when links fail over.
Reference
0ae134734e9d