New B200 spot capacity is live in US East from $1.69 per GPU-hour. See availability
Scheduled maintenance

Network fabric upgrade — US East

Leaf switches in US East (Virginia) will be upgraded pair by pair. Each rack loses one of its two uplinks for a few minutes; traffic continues on the other.

Reference 74e26f357e9a · US East (Virginia) · Updated just now

Status
CompletedCompleted — last update 18 Mar 2025, 09:21 UTC
Started
18 Mar, 07:00Tuesday 18 March 2025 UTC
Duration
2 h 21 minEnded 18 Mar 2025, 09:21 UTC
Components
1Network and public IPs — US East (Virginia)
Timeline

The window, as announced and as it ran.

Completed3 updates · UTC
  1. CompletedThe maintenance is complete and every component is back to normal operation.18 Mar, 09:21
  2. In progressThe maintenance window has started.18 Mar, 07:00
  3. ScheduledLeaf switches in US East (Virginia) will be upgraded pair by pair. Each rack loses one of its two uplinks for a few minutes; traffic continues on the other. Expected impact: Up to 30 seconds of packet loss per rack, twice, when links fail over.11 Mar, 07:00

Affected components

Details

Type
Scheduled maintenance
Started
18 Mar 2025, 07:00 UTC
Ended
18 Mar 2025, 09:21 UTC
Region
US East (Virginia)
Expected impact
Up to 30 seconds of packet loss per rack, twice, when links fail over.
Reference
74e26f357e9a