New B200 spot capacity is live in US East from $1.69 per GPU-hour. See availability
Scheduled maintenance

Network fabric upgrade — EU Central

Leaf switches in EU Central (Frankfurt) will be upgraded pair by pair. Each rack loses one of its two uplinks for a few minutes; traffic continues on the other.

Reference 57725b9c279e · EU Central (Frankfurt) · Updated just now

Status
CompletedCompleted — last update 15 Apr 2025, 03:09 UTC
Started
15 Apr, 01:00Tuesday 15 April 2025 UTC
Duration
2 h 9 minEnded 15 Apr 2025, 03:09 UTC
Components
1Network and public IPs — EU Central (Frankfurt)
Timeline

The window, as announced and as it ran.

Completed3 updates · UTC
  1. CompletedThe maintenance is complete and every component is back to normal operation.15 Apr, 03:09
  2. In progressThe maintenance window has started.15 Apr, 01:00
  3. ScheduledLeaf switches in EU Central (Frankfurt) will be upgraded pair by pair. Each rack loses one of its two uplinks for a few minutes; traffic continues on the other. Expected impact: Up to 30 seconds of packet loss per rack, twice, when links fail over.8 Apr, 01:00

Affected components

Details

Type
Scheduled maintenance
Started
15 Apr 2025, 01:00 UTC
Ended
15 Apr 2025, 03:09 UTC
Region
EU Central (Frankfurt)
Expected impact
Up to 30 seconds of packet loss per rack, twice, when links fail over.
Reference
57725b9c279e